[The Pulse] 2018 Business Continuity Plan (mid-year revision) Now Available

[The Pulse] 2018 Business Continuity Plan (mid-year revision) Now Available

CU*Answers Business Continuity Plan: 2018 Release Now Available   As your core data processor, we continue to invest in high availability and recovery strategies to ensure that the products and services you count on us for are there when you need them. Implementing those strategies and responding when uncertainty happens requires a well-designed and thoroughly… Read more »

Jul 27, 2018

[The Pulse] HA Rollover Results Now Available

[The Pulse] HA Rollover Results Now Available

HA Rollover Results Now Available Rollover: May 20 – 23 Now available for your review is a summary of the recent HA (high-availability) rollover event, performed May 20 – 23.  In the report, you will find details about the exercise and hardware upgrades, including challenges observed, lessons learned, and recommendations for improving the rollover process…. Read more »

Jun 28, 2018

[The Pulse] Reminder: HA Rollover Scheduled for May 20-23

[The Pulse] Reminder: HA Rollover Scheduled for May 20-23

High Availability Rollover Scheduled Sunday, May 20 – Wednesday, May 23   Originally scheduled for March 25-28, the next CU*Answers Rollover event has been rescheduled for May 20-23.  During this rollover event, we will redirect CU*BASE core-processing from our primary production data center to systems at our high-availability (HA) data center. The rollover process will… Read more »

May 15, 2018

[The Pulse] HA Rollover Scheduled for May 20-23

[The Pulse] HA Rollover Scheduled for May 20-23

High Availability Rollover Scheduled Sunday, May 20 – Wednesday, May 23   Originally scheduled for March 25-28, the next CU*Answers Rollover event has been rescheduled for May 20-23.  During this rollover event, we will redirect CU*BASE core-processing from our primary production data center to systems at our high-availability (HA) data center. The rollover process will… Read more »

May 2, 2018

[The Pulse] Reminder: HA Rollover Scheduled for March 25-28

[The Pulse] Reminder: HA Rollover Scheduled for March 25-28

High Availability Rollover Scheduled Sunday, March 25 – Wednesday, March 28   During this rollover event, we will redirect CU*BASE core-processing from our primary production data center to systems at our high-availability (HA) data center. The rollover process will begin at 10:00 PM ET on Sunday, March 25. We will continue providing live production of… Read more »

Mar 15, 2018

[The Pulse] HA Rollover Scheduled for March 25-28

[The Pulse] HA Rollover Scheduled for March 25-28

High Availability Rollover Scheduled Sunday, March 25 – Wednesday, March 28   During this rollover event, we will redirect CU*BASE core-processing from our primary production data center to systems at our high-availability (HA) data center. The rollover process will begin at 10:00 PM ET on Sunday, March 25. We will continue providing live production of… Read more »

Mar 7, 2018

[The Pulse] 2018 Business Continuity Plan Now Available

[The Pulse] 2018 Business Continuity Plan Now Available

CU*Answers Business Continuity Plan: 2018 Release Now Available   As your core data processor, we continue to invest in high availability and recovery strategies to ensure that the products and services you count on us for are there when you need them. Implementing those strategies and responding when uncertainty happens requires a well-designed and thoroughly… Read more »

Jan 29, 2018

[The Pulse] HA Rollover Results Now Available

[The Pulse] HA Rollover Results Now Available

HA Rollover Results Now Available Rollover: September 17 – 20 Now available for your review is a summary of the recent HA (high-availability) rollover event, performed September 17 – 20.  In the report, you will find details about the exercise, including challenges observed, lessons learned, and recommendations for improving the rollover process. HA Rollover Results… Read more »

Oct 27, 2017

Reminder: Complete a Connectivity Test for this Sunday’s HA Rollover

Reminder: Complete a Connectivity Test for this Sunday’s HA Rollover

The next CU*Answers (HA) High Availability Rollover is scheduled for September 17-20.  During this rollover event, there will be an interruption lasting approximately 30-60 minutes for CU*BASE core-processing applications, including CU*Talk audio response and It’s Me 247 online banking (a splash page will be presented). As a proactive step, we are recommending that you test connectivity… Read more »

Sep 12, 2017

[The Pulse] HA Rollover Scheduled for Sunday, September 17

[The Pulse] HA Rollover Scheduled for Sunday, September 17

High Availability Rollover Scheduled Sunday, September 17 – Wednesday September 20 During this rollover event, we will redirect CU*BASE core-processing from our primary production data center to systems at our high-availability (HA) data center. The rollover process will begin at 10 PM ET on Sunday, September 17. We will continue providing live production of CU*BASE… Read more »

Aug 31, 2017