Don’t Forget: The Next HA Rollover is This Weekend – We Need You to Perform a Connectivity Test!

Twice each year, CU*Answers tests our ability to redirect CU*BASE core-processing from our production data center to our high-availability (HA) data center.  The next HA rollover is scheduled for Sunday, February 6th.

This rollover will enable support teams to perform planned network maintenance at the primary production data center without disrupting core processing.  The rollover will begin at 2:00 AM ET on Sunday, February 6th with the rollback scheduled for 2:00 AM ET on Sunday, February 13th.

Prior to this rollover, we strongly encourage that someone at each branch tests connectivity from a GOLD workstation.  Additionally, if your credit union has any employees who are working remotely, we recommend asking them to perform the connectivity test as well.  Use the links below to complete one or both of the connectivity tests.

Please contact the CU*Answers Network Services Help Desk at helpdesk@cuanswers.com if the tests above are unsuccessful.  Failure to complete the tests may result in CU*BASE/GOLD connectivity issues on the morning following the February 6th rollover event.

If you have questions or would like to know more about the CU*Answers High Availability program in general, additional information is provided on our website, or feel free to contact a member of the Business Continuity Team.

[The Pulse] HA Rollover Results Now Available

[The Pulse] HA Rollover Results Now Available

HA Rollover Results Now Available HA Rollover: March 10 – April 7 Now available for your review is a summary of the recent CU*Answers HA (high availability) rollover event performed March 10th to April 7th for the CU*BASE core processing environment.  In this report, you will find details about the exercise, including challenges observed, lessons… Read more »

Apr 22, 2024

HA Rollback Completed – Report Coming Soon

HA Rollback Completed – Report Coming Soon

The HA Rollback was successfully completed on Sunday, April 7th.  This marks the conclusion of the March HA Rollover event. In the days ahead, we will be preparing a gap analysis report on the HA Rollover event, which will include details about the exercise, challenges observed, lessons learned, and recommendations for improving the process.  An… Read more »

Apr 8, 2024

Reminder: HA Rollback This Weekend

Reminder: HA Rollback This Weekend

Rescheduled from our original targeted date of March 17th, the high-availability rollback event will now be occurring this weekend.  The rollback process will begin Sunday, April 7th at 3:00 AM ET. During this time, there will be a period of approximately 60 to 90 minutes that will include an interruption to the following services: CU*BASE/GOLD,… Read more »

Apr 4, 2024

Reminder: HA Rollback This Weekend

Reminder: HA Rollback This Weekend

This is a reminder of the high-availability rollback event that will be occurring this weekend.  The rollback process will begin Sunday, March 17th at 3:00 AM ET. During this time, there will be a period of approximately 60 to 90 minutes that will include an interruption to the following services: CU*BASE/GOLD, CU*Talk audio response and… Read more »

Mar 14, 2024

HA Rollover Event this Weekend – Updates to be Posted on CU*BASE Alerts Page

HA Rollover Event this Weekend – Updates to be Posted on CU*BASE Alerts Page

Don’t forget: this weekend, we will be testing our ability to redirect CU*BASE core-processing from our production data center to our high-availability (HA) data center.  The Rollover event is scheduled to begin at 1:00 AM ET on Sunday, March 10th.  Once completed, CU*BASE core-processing will be provided from systems at the HA data center for… Read more »

Mar 7, 2024

Reminder: The Next HA Rollover is Coming March 10th – We Need You to Perform a Connectivity Test!

Reminder: The Next HA Rollover is Coming March 10th – We Need You to Perform a Connectivity Test!

Twice each year, CU*Answers tests our ability to redirect CU*BASE core-processing from our production data center in Kentwood, MI to our high-availability (HA) data center in Yankton, SD.  The next HA rollover is scheduled for Sunday, March 10th. The rollover is scheduled to begin at 1:00 AM ET on Sunday, March 10th with the rollback… Read more »

Feb 27, 2024

Network Maintenance Project Scheduled for Sunday, March 10th

Network Maintenance Project Scheduled for Sunday, March 10th

As a reminder, CU*Answers will be performing our next CU*BASE high-availability (HA) rollover on Sunday, March 10th.   That same morning, teams will be rolling over online and mobile banking systems to servers at our secondary data center. These rollovers are in preparation for a maintenance project at our production data center that will include… Read more »

Feb 27, 2024

Reminder: The Next HA Rollover is Coming March 10th – We Need You to Perform a Connectivity Test!

Reminder: The Next HA Rollover is Coming March 10th – We Need You to Perform a Connectivity Test!

Twice each year, CU*Answers tests our ability to redirect CU*BASE core-processing from our production data center in Kentwood, MI to our high-availability (HA) data center in Yankton, SD.  The next HA rollover is scheduled for Sunday, March 10th. The rollover is scheduled to begin at 1:00 AM ET on Sunday, March 10th with the rollback… Read more »

Feb 27, 2024

Network Maintenance Project Scheduled for Sunday, March 10th

Network Maintenance Project Scheduled for Sunday, March 10th

As a reminder, CU*Answers will be performing our next CU*BASE high-availability (HA) rollover on Sunday, March 10th.   That same morning, teams will be rolling over online and mobile banking systems to servers at our secondary data center. These rollovers are in preparation for a maintenance project at our production data center that will include… Read more »

Feb 27, 2024

Reminder: The Next HA Rollover is Coming March 10th – We Need You to Perform a Connectivity Test!

Reminder: The Next HA Rollover is Coming March 10th – We Need You to Perform a Connectivity Test!

Twice each year, CU*Answers tests our ability to redirect CU*BASE core-processing from our production data center in Kentwood, MI to our high-availability (HA) data center in Yankton, SD.  The next HA rollover is scheduled for Sunday, March 10th. The rollover is scheduled to begin at 1:00 AM ET on Sunday, March 10th with the rollback… Read more »

Feb 21, 2024